Cooler temps hamper Lecanto Goverment Complex resurfacing

Due to the cold morning temperatures the resurfacing project at the Lecanto Government Building Parking Lots along with West Sovereign Path has been extended to include Friday, March 9, 2018.

The work began on Saturday, March 3, 2018, and work will continue intermittently throughout the month of March. The work has been planned in phases in order minimize disruption to normal business. We ask for your patience and cooperation as we work to complete this project.

The updated schedule for the repaving project is as follows:

Thursday, March 8 and Friday, March, 9, 2018:

  • Employee Parking Lot repaved. Alternate parking will be available for employees at the basketball courts behind the LGB and grass areas as available. Employee carpooling and off-site parking is recommended where feasible.
  • W. Sovereign Path repaved. The road will be open to one lane traffic during the project. (Vehicles will enter from Saunders Way and exit to Educational Path). This work is expected to be completed by the end of the day.

Friday, March 30, 2018:

  • County offices are closed for GoodFriday. Citizen Parking Lot repaving takes place.  The Citizen Parking Lot will open for business on Monday, April 2, 2018.